Italy’s second MACSE auction clears 12% lower than first; Enel, BW ESS/A2A and Field among winners

Summary

Italy's TSO Terna concluded its second MACSE auction, awarding 15-year contracts for 16GWh of large-scale battery storage at an average clearing price 12% below the 2025 round. Enel won three projects totaling 7,336MWh (45% of capacity), while A2A secured four projects totaling 2,608MWh.

Italy TSO Terna has concluded its second MACSE auction, procuring 16GWh of long-term BESS capacity at a lower clearing price than 2025’s auction. 

Terna announced the results of the Meccanismo di Approvvigionamento di Capacità di Stoccaggio Elettrico (MACSE) auction yesterday (24 November), handing out 15-year revenue contracts to large-scale battery energy storage system (BESS) projects. 

The auction was 60% larger than the first auction in 2025 and, contrary to some predictions, cleared 12% lower than the previous one. Terna procured 16GWh of storage in Southern Italy and its islands at an average clearing price of €11,382/MWh-year (US$12,449), 12% lower than the €12,959/MWh-year in 2025. It is a pay-as-bid auction. 

Of the 16GWh awarded: 

  • 2.8GWh is in Central-South, with an average price of €10,716/MWh-year
  • 9.6GWh is in South and Calabria, with an average of €11,575/MWh-year
  • 3 GWh in Sicily, with an average of €11,467/MWh-year
  • 0.5GWh (approximately) in Sardinia, with an average of €10,925/MWh/year 

Enel has also released a table of the 16 winning projects with names and capacities, see the full table below.

Project companyRegionAwarded capacity [MWh]Total capacity [MWh]Awarded power [MW]Project duration (hours)
ACL SPV 2 S.R.L.South and Calabria888903.467143.7546.28
A2A ENERGIEFUTURE SPASouth and Calabria364388.68507.77
A2A STORAGE SRLSouth and Calabria313330.58942.5277.77
A2A STORAGE SRLSicily1,0741,117.441507.45
A2A STORAGE SRLSicily857852.791505.69
BESS BY ERRY SRLSouth and Calabria1,6671,718.866254.7826.75
ENEL PRODUZIONE S.P.A.Sicily1,1371,160.65181.926.38
ENEL PRODUZIONE S.P.A.South and Calabria3,3993,460.866549.5176.30
ENEL PRODUZIONE S.P.A.Central South2,8002,858.22446.6546.40
FIELD MELFISouth and Calabria1,1381,160.742181.9356.38
FIVE-E ITALY ORANGE 2South and Calabria539556.38785.6366.50
NARDO’ SOLAR ENERGY SRLSouth and Calabria120133.14816.6448.00
NARDO’ SOLAR ENERGY SRLSouth and Calabria120133.14816.6448.00
PVEXO APOLLO 2 SRLSouth and Calabria623648.642108.0456.00
SATURN SRLSouth and Calabria430432.44866.536.50
W SELARGIUSSardinia531553.12589.4476.18
Total16,000

Going off the names, state-owned power group Enel won three projects totalling 7,336MWh of capacity, 45% of the total. Another state-owned company, utility A2A, won contracts for four projects totalling 2,608MWh of capacity, 16% of the total. BW ESS then announced today that those latter projects are part of a joint venture (JV) it has with A2A.

UK-headquartered BESS developer-operator Field also has a project in there, totalling 1,138MWh of capacity. 

Obligations for the 2026 auction start in 2029, and in 2028 for the 2025 auction. The auction provides guaranteed revenues, but operators have to bid in more-or-less all of their project’s capacity leaving little room for merchant exposure. 

Terna said that the volumes procured were calculated to ensure that the costs of the new capacity is lower than the benefit associated with the reduction in gas-fired generation costs (which the auction will enable). 

The auction’s results and implications will be a big talking point at next week’s Battery Asset Management Summit Europe 2026 in Rome (head to the website and use our discount code ESN20 for 20% off tickets).

You can go and read the full results report on Terna’s website (in Italian) here. 

Industry reaction and analysis 

“Pretty remarkable results given rising interest rates and the potential for cost increases in storage supply chains… A win for centrally procured storage fleets & consumers,” said analytics firm Modo Energy’s Ed Porter on LinkedIn.

Álvaro Galván de Miguel, M&A at South Korean firm Hanwha Energy Europe, said that the volume in competition was softer but the volume in price was fiercer. The offers were 2.7x the available capacity, versus 4x last year. 

“Bidders were careful with how much they offered, not with the price. Battery costs keep falling, and winners are accepting returns close to a regulated asset,” he said. 

Regarding the winners, project companies often have generic names without the ultimate parent company’s name in there, so some companies’ market share in the auction could be higher. Similarly there could be well-known companies in there under a generic name. 

Academic Frederico Santi said on LinkedIn that Enel and A2A’s combined share is actually around 85%, though this has not been reported elsewhere. 

In last year’s auction, Enel won just over half of the capacity (see our ESN Premium analysis at the time here). 

What returns are possible? 

Meanwhile, a study by the Politecnico di Milano’s Energy & Strategy research centre reported just before the auction that low prices in the auction could leave BESS projects struggling to recover costs. 

James Wong, European director for Chinese power solutions firm Eaglierise Electric, also asked the question of what returns can realistically be made at those prices. He said the auction shows how attractive contracted revenues are, how big the BESS pipeline has become, and how Italy is positioning itself as a unique market for storage.

“MACSE still sells certainty, but that certainty is cheaper than it was a week ago. Fifteen years of contracted revenue can still support leverage, but equity returns will be thinner. The contest is still about cost of capital and EPC and equipment cost control, and the bar just got higher,” he said.

“The real signal is the depth of supply. 67GWh qualified and 43GWh bid for 16GWh, which shows how thick the project pipeline already is in southern Italy and the islands. If later rounds do not add much more volume, clearing prices could still have room to fall.” 

“The contrast with Southeast Europe (SEE) still holds, and the split is clearer: Italy has just marked down the price of contracted revenue, while SEE is still digesting tighter spreads. Cheap long-term capital will lean even more toward markets like this. To earn a trading premium, capital still has to stay in SEE and turn floors or tolling into bankable structures.” 

“A question for peers: at €11,382 for a 15-year contract, what equity return can you still make at your cost of capital?” 

Share this article

The Green Wire Weekly

Weekly deep dive into sustainable transport.

Comments

No approved comments yet. Be the first to comment.

Leave A Reply

Comments are temporarily unavailable.

Related Coverage