Home › Electric Vehicles › DTE Energy Opens Bidding for Up to 150 MW of New Michigan Solar Projects
Electric Vehicles

DTE Energy Opens Bidding for Up to 150 MW of New Michigan Solar Projects

calendar_today
schedule 2 min read
Detailed view of ChargePoint electric vehicle charging plugs at a station outdoors.

Summary

DTE Energy has launched a competitive bidding process for up to 150 megawatts of new Michigan solar generation aimed at creating construction jobs and lowering customer fuel costs. Proposals are due January 19, 2027, with contracts expected in mid-2027 and commercial operation required by June 30, 2030.

The company launches a competitive bidding process for up to 150 megawatts of new Michigan solar energy.

DTE Energy has announced plans to add up to 150 megawatts of new solar energy in Michigan, creating construction jobs, supporting local communities, and saving customers money on fuel costs.

Because solar generation does not require fuel, the new projects will help reduce the company’s exposure to changing fuel prices over their operating lives. The projects will also support DTE’s work to provide customers with energy that is reliable, increasingly clean, and affordable.

“These projects are an investment in Michigan and the communities we’re proud to serve. By producing more Michigan-made energy that doesn’t require us to purchase fuel, we can help lower energy costs for our customers and reduce our reliance on fuel from outside our state. At the same time, these projects will create good jobs and bring new investment and tax revenue into local communities, providing more resources for schools, first responders and the services Michigan families count on every day.”

Project and bidding details

DTE is seeking competitive proposals for up to 150 megawatts of new Michigan-based solar generation. The procurement supports the requirements of the settlement agreement in Michigan Public Service Commission Case No. U-21662, approved May 15, 2025.

Projects must achieve commercial operation by June 30, 2030, be located in Michigan and connect to either the MISO transmission system or DTE’s distribution system. Interested bidders can register and obtain additional information through PowerAdvocate. Proposals are due Jan. 19, 2027, and DTE expects to execute contracts in the second or third quarter of 2027.

DTE is Michigan’s leading producer of and investor in renewable energy, generating enough clean energy from wind and solar to power nearly 1 million homes. As the company works toward net zero carbon emissions, it remains committed to growing its renewable energy portfolio while maintaining a balanced mix of energy resources that supports reliability and affordability for customers. DTE’s 2026 Integrated Resource Plan builds on that commitment, calling for an additional 15 gigawatts of renewable energy by 2042.

Share this article

The Green Wire Weekly

Weekly deep dive into sustainable transport.

Comments

No approved comments yet. Be the first to comment.

Leave A Reply

Comments are temporarily unavailable.

Related Coverage