Senate passes third resolution demanding release of redacted NRMA EV charging report
Summary
The Senate has again voted to force release of NRMA's "Grit in the Gears" report, which examined why its $78 million national EV charging network fell short of targets. The report remains almost entirely redacted on the government website, with the energy minister citing commercial sensitivity.
The Senate has passed a third resolution seeking the release of the “Grit in the Gears” report written by the NRMA motoring group, which is believed to have identified the problems that prevented it from delivering the proposed national network of EV chargers as planned.
The Senate first called for the release of the Grit in the Gears report in September, then set an October deadline, and this week put a new deadline of November 25 (Wednesday). The motion was put forward by the federal Coalition approved in a vote 35-20 with the support of the Greens and independents.
The request has previously been refused by energy and climate minister Chris Bowen on the basis that its content is commercially sensitive and claiming public immunity. There is no evidence that the report has been released after the latest request.
As The Driven reported last month, The Grit in the Gears report – subtitled “Lessons from the frontline of building a national EV network” – delves into how NRMA came up short in the $78 million plan to roll out 117 EV charging stations across the nation. Around 62 have so far been completed, according to an NRMA spokesperson.
The 21-page report has actually been published on the Department of Climate Change, Energy and the Environment website, but is totally redacted, bar one single line that identifies the average cost of the charging installations – $350,000.
The NRMA won the contract to roll out the national charging network in April, 2023, with $39 million in funding from the Australian Renewable Energy Agency, and agreeing to match that sum with its own money. The plan was to build a network around Australia, to ensure there was a charger every 150 km along major routes.
But the program ran into significant issues, particularly in regional and off-grid areas. According to a report published in the AFR in March only 45 of the EV charging stations had been installed, little more than one third of the target. That has now risen to 62 and the NRMA says work continues on the other installations.
One report that was published on ARENA’s website in late December, 2024, underlined the challenges the rollout of charging networks faced due to hardware issues (often not discovered until after deployment), supply chains, local council regulations, and the delays in approvals from local electricity networks.
“One of the most significant hurdles faced during the rollout of the National EV Charging Infrastructure Program was hardware design issues caused by original equipment manufacturers (OEMs),” the report says.
“The hardware initially chosen for the charging stations exhibited critical flaws that necessitated complete redesigns of several charging sites. These design issues were not identified until after deployment, leading to delays in the installation schedule.
“As a result, NRMA had to renegotiate with site hosts to accommodate the redesigned infrastructure, further complicating the timeline.
“The flaws in hardware design not only affected the efficiency of individual charging stations but also revealed a larger issue within the industry: new and emerging technologies often undergo extensive testing only after they are deployed in the field. This gap in the testing and design process led to unanticipated issues that could have been avoided with more rigorous pre-deployment validation.”
The withdrawal of Tritium and Freewire from the Australian market also complicated matters. On top of that, delays were experienced in planning, site approvals and grid connections.
“Issues such as crown land negotiations, floodplain impacts, and unrecorded underground utilities have only surfaced during detailed site assessments, resulting in significant delays,” the report says.
“Additionally, the need for DNSP connections to the grid has created bottlenecks in the program’s timeline, as the approval process for new technologies such as behind-the-meter (BTM) batteries has been slow. This has resulted in delays at several locations, requiring adjustments to the project timeline and budget.
“Securing timely connections from DNSPS has been one of the most time-consuming aspects of the project. The uncertainty surrounding tariffs and the extended timelines for connection upgrades have created a bottleneck, leading to prolonged delays.
“In addition to these regulatory hurdles, there has been concern about the lower-than-expected utilisation rates at certain remote sites. This underscores the need for more strategic site selection, as some locations have proven less viable than anticipated due to limited demand.”