AGL's 500MWh Abermain battery storage project wins federal environmental clearance in Queensland

calendar_today
schedule 3 min read
AGL’s 500MWh Abermain battery storage system cleared under Australia’s EPBC Act

Summary

AGL Energy has secured federal environmental approval under Australia's EPBC Act for its 125MW/500MWh Abermain battery energy storage system west of Brisbane. The decision, which requires no further federal assessment, advances AGL's growing Queensland storage pipeline following its acquisition of developer Firm Power.

AGL Energy has received federal environmental clearance for a 500MWh battery energy storage system (BESS) in Queensland under Australia’s EPBC Act.

The Abermain Battery Project, which was referred with a power output of 125MW and a 4-hour duration, would be built at 161-173 Holdsworth Road, Tivoli, in the Ipswich City Council area west of Brisbane.

A decision notice found the project is “not a controlled action” under section 75 of the Environment Protection and Biodiversity Conservation (EPBC) Act, meaning it needs no further federal assessment.

The decision was made by Declan O’Connor-Cox, branch head, Environment Assessments Queensland, and lapses in November 2031 if the project has not substantially started by then.

The proponent is Abermain BESS OpCo Pty Ltd, a wholly owned AGL entity, which referred the 125MW/500MWh Abermain BESS earlier this year without proposing environmental offsets, as AGL did not consider it a controlled action.

The referral said the BESS would connect to the National Electricity Market (NEM) through Powerlink’s Abermain Substation, about 100m north-west of the site, via a new on-site 275/33kV substation and an underground line.

Powerlink, the Queensland government-owned transmission network operator, is separately developing that connection, which it would build, own and operate.

The referral described enclosed lithium-ion battery storage units with power conversion systems (PCS), transformers, inverters and switchgear.

Construction would take up to 18 months, followed by an operating life of up to 30 years. The disturbance footprint covers about 3.3 hectares, around 1.2 hectares of it degraded eucalyptus and acacia woodland, with koala-exclusion fencing among the proposed mitigation measures.

Ipswich City Council granted development approval for the project on 3 November 2023.

It was originally developed by Firm Power, which AGL agreed to acquire in August 2024 for AU$250 million (US$165.5 million), adding a 5.8GW pipeline of grid-scale projects, 2.7GW of it in Queensland.

AGL’s Queensland pipeline grows

Abermain is AGL’s second Queensland BESS to clear the EPBC Act, after the 500MW/2,000MWh Tuckeroo BESS at Hopeland in the Western Downs, which was also ruled not to be a controlled action.

Western Downs Regional Council granted development approval for Tuckeroo in March 2025, and AGL targeted commercial operation in the second half of 2027 when it referred the project.

Powerlink referred a 1.8km underground 275kV line connecting Tuckeroo to the Western Downs Substation in October 2025, as it is doing for Abermain.

AGL has since referred its 500MW/2,000MWh Mount Britton BESS near Nebo in central Queensland, where its referral said the project could directly affect species including the koala and greater glider.

In New South Wales, AGL began commissioning its 1,000MWh grid-forming Liddell BESS earlier this year, backed by AU$35 million in funding from the Australian Renewable Energy Agency (ARENA), the federal renewables funding body. It has since been brought online.

Closer to Abermain, CleanCo, the Queensland government-owned generator, opened its 250MW/500MWh Swanbank BESS in February 2026 on a former coal power station site, using Tesla Megapack units.

Firm Power also originated the 500MW/1,000MWh Blackstone Battery in Ipswich’s Swanbank industrial area, which Octopus Australia bought in October 2023 and took through Ipswich City Council planning approval in July 2025.

Other Queensland projects have received the same federal ruling. The 1,600MWh grid-forming Rutherglen Battery from Gryphon Energy, Red Hill Renewable Energy and Ampyr Energy Australia near Gladstone was found not to be a controlled action in March.

Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.

Share this article

The Green Wire Weekly

Weekly deep dive into sustainable transport.

Comments

No approved comments yet. Be the first to comment.

Leave A Reply

Comments are temporarily unavailable.

Related Coverage