European BESS Market Shifts from Tolls to Floors as Operators Grapple with State-of-Charge Challenges

calendar_today
schedule 6 min read
European BESS market moves from tolls to floors, ‘operators only just beginning to understand’ SOC challenges

Summary

An Everoze partner says European battery storage operators are moving from tolling deals to floor arrangements as their market experience grows, though state-of-charge management remains a persistent challenge. The interview also covers Italy's second MACSE auction and evolving best practices in BESS asset management.

Nicolas Chouleur, partner at advisory firm Everoze, shares his views on the key trends and challenges in European BESS asset management today.  

In this Q&A, he says that asset operators in Europe are generally moving from tolls to floors as they gain experience in the market, while state-of-charge challenges persist in the industry. He also shared his views on Italy’s second MACSE auction, which is taking place over the course of today (24 November).

Chouleur will be speaking at the Battery Asset Management Summit Europe 2026 in Rome which is now right around the corner, running on 2-3 December. Asset management and MACSE will be big talking points at the event.

Use our discount code ESN20 for a 20% discount on tickets. You can catch Everoze’s Nicolas Chouleur on the ‘Warranties at a Crossroads: One Fleet’s Degradation Data, Opened Up’ case study and panel session on Day Two.  

Chouleur has worked on battery energy storage system (BESS) projects largely in France but also across Europe including Belgium, Spain, Portugal, Estonia and Italy.  

Industry improving technical understanding and management of technology

Energy-Storage.news: How has BESS asset management best practice evolved in the past three years?   

Nicolas Chouleur: As technical adviser, we see an evolution in the expertise of the developers/operators of BESS assets. The most positive evolution is a better understanding of [the] technicality of batteries and technical management to ensure long term efficiency.  

What are the key policy, regulation and market design changes you need to keep track of when it comes to formulating your BESS asset management strategy?   

We are not developers or asset managers ourselves, so may not have the full picture. The biggest issue from our point of view is certainly the grid connection: difficulty to get capacity, and lead time to get connected. Connection of batteries should be a priority for distribution system operators (DSO) and transmission system operators (TSO). 

What is your current approach to maximising returns from your BESS, and what key performance indicators drive your operational decisions?  

We are not involved in those decisions. But from a long term profitability perspective, a focus on the warranties and on battery cycling is key. 

What are your views on the MACSE auction and what impact it will have on the market?  

The most interesting outcome may be that MACSE doesn’t fight the merchant market. The success of MACSE shouldn’t ultimately be measured by achieving the lowest possible auction price. It should be measured by whether it delivers the right storage, in the right locations, on time, while maintaining enough competition and investment signals for the wider Italian BESS market. 

Industry approach to degradation, warranties is evolving

How do you balance profitable market participation with preserving battery cell health, and what role do optimisation technologies play in this decision-making process?   

From the lenders’ interests’ perspective, we always make sure that if there is an opportunity of generating higher revenues by cycling more, there will be a cash-back mechanism to anticipate debt payment. You don’t want to battery to lose state-of-health (SOH) warranty before the debt has been reimbursed.  

As the industry matures, how is the approach to managing degradation evolving?  

Only a few years ago, the material, SOH and round-trip-efficiency (RTE) warranties were included in the EPC price. You paid a large amount as part of CAPEX for the full-battery life warranty coverage. 

Now, the most common situation is two years of full warranty included with EPC and then an annual fee. The lenders generally ask the sponsors to subscribe to the full warranty package. 

In most recent projects, we see sponsors negotiating SOH and RTE still (we believe it is mandatory), but not the product warranty extension, relying rather on spare parts stock and MRA. This is a similar trend to what we saw in solar PV 10-15 years ago.  

How are performance warranties evolving to keep up with the pace of industry development and give operators the flexibility to maximise returns?  

We have not noticed particular change in the performance warranties over the recent years. The point of negotiation is always around the flexibility mechanism. What we don’t see anymore is no flexibility at all, which was still often the case some years ago and was a red flag in our reviews. 

How big a challenge is accurate state-of-charge (SOC) measurement, and how are operators solving this / mitigating the risks?  

It is a big deal, and I think the assets operators are only [at the] beginning of understanding this. Since at beginning of life, the energy capacity is generally oversized, it may not be an issue. But with time, as capacity goes down, not handling SOC properly may lead to loss in capacity and revenues.  

We are supporting clients with commissioning and have seen some tests where the cells were not properly balanced and the EPC had to ‘tweak’ the charge/discharge cycle to reach capacity. But since most of the large projects we have worked on are still under construction or have started operation relatively recently, within the past year to three years, it is still too early to have a view on the potential long-term impact and remedies. But when you see gaps at commissioning, you are up for animated discussions between the asset’s owner and the EPC.

Is there an emerging consensus on the augment-or-overbuild choice?  

Not that we are aware of. The price of batteries has fallen significantly so we now most often see oversizing. Most of the developers’ projects we have reviewed also negotiate larger areas to be leased so, in the future, they will have the possibility to augment, from 2-hours to 4-hours [duration] for example. But it’s rather a land lease anticipation than a clear design decision. 

Optimisation and risk-sharing

How much of a challenge is it to assess optimiser performance, and how is this developing?  

We are not operating assets, so [we are] not directly involved. What we see is generally short-term contracts with the possibility to terminate early as well. So, projects’ developers anticipate the possibility to launch regular tenders for the route-to-market (RTM) provider. 

What type of revenue contract structures are currently dominating, and which will we see in the market going forward (floors, tolls, swaps etc)?   

In recent years, we have seen a move from tolling agreement to floor-plus-profit share. Almost every first project for a company is also relying on tolling, then when developers get more experienced, they move to floor-plus-profit share. On a few projects we have seen full merchant route-to-market agreement, but to date those remain exceptions.

Share this article

The Green Wire Weekly

Weekly deep dive into sustainable transport.

Comments

No approved comments yet. Be the first to comment.

Leave A Reply

Comments are temporarily unavailable.

Related Coverage